Construction in Progress (Details Narrative)

v3.8.0.1
Construction in Progress (Details Narrative) - USD ($)
3 Months Ended
Oct. 04, 2017
Aug. 14, 2017
Jun. 08, 2017
Mar. 31, 2018
Payment to contractor       $ 455,800
Construction is estimated to be completed       The construction at the Dorado location was completed March 24, 2018; and the construction was completed at Carolina and Andalucia on May 14, 2018. The construction on the Fajardo location began on March 15, 2018 and is anticipated to be completed by May 31, 2018.
Carolina [Member]        
Construction contracts     $ 123,700  
Dorado [Member]        
Construction contracts     $ 100,075  
Andalucia [Member]        
Construction contracts   $ 117,200    
Fajardo [Member]        
Construction contracts $ 127,600